Taking Time Off the Critical Path: why offsite manufacture is the more efficient route to programme delivery 

Home » News » Taking Time Off the Critical Path: why offsite manufacture is the more efficient route to programme delivery 

Our Managing Director for SES Manufacturing, Paul Cooper has shared his thinking on how offsite manufacture can protect programme delivery in the November issue of the Offsite Magazine.  

In his article, “Taking Time Off the Critical Path,” Paul explains why moving MEP fabrication and assembly into a controlled factory environment removes the dependencies that put programmes at risk – and what that means for speed, safety and certainty on site. 

The problem with building in sequence 

In a traditional approach, plant rooms, risers and other services installations are built in situ, one trade after another. When any one activity slips, everything behind it slips too, and the delay lands on the critical path. The more services-heavy the building, the more exposed the programme becomes. 

Breaking the dependency 

Offsite manufacture changes the sequence. Once the design is agreed, fabrication, assembly, pipework, electrical installation and containment can begin in the factory, progressing in parallel with groundworks, structural work and the building envelope on site. As the article puts it: “Offsite manufacture does not simply complete the same work more quickly; it moves most of the activity out of the programme’s most constrained environment and into one where it can progress independently and safely.” 

The proof is in the numbers 

In 2025, SES Manufacturing produced 32,890 products in a controlled factory environment, removing 309,801 hours from site. Those hours were used more productively to improve speed, safety and quality. 

The approach was recently put into practice at One Hanover Street, a listed building at the junction of Regent Street and Hanover Street in London’s West End. SES Manufacturing produced a fully packaged mechanical plant room offsite, which was transported to central London, lifted onto the dedicated plant level and installed in three sections. The result was 2,952 hours removed from site and reduced risk from working at height – demonstrating how integrated delivery and offsite manufacture can support complex refurbishment projects in constrained city-centre locations. 

Certainty as well as speed 

The article highlights that offsite manufacture offers more than programme savings: 

A more efficient route to delivery 

Site is where risk concentrates. Offsite manufacture offers a practical way to reduce that concentration by doing more of the work where conditions can be controlled, at the same time as everything else. For project teams looking to protect their programme, the question is no longer whether offsite manufacture can deliver, but how much of the critical path they are prepared to take off site. 